Skip to main content

Narang Realty projects in Mumbai

MahaRERA projects by Narang Realty registered 2024–2026 in Mumbai.

Projects registered with MahaRERA3
Total units across these projects792
Full record

MahaRERA projects registered 2024–2026 in Mumbai

Completed without extending the possession date0
Completed after an extension0
Lapsed0
Under construction3
Possession date extended on the builder's application0
MahaRERA complaints (filed by or against the builder), all Narang Realty projects0 (0 of 3 projects)
What these mean
  • Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
  • Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
  • Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
  • Under construction: MahaRERA status Active.
  • Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
  • Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
  • MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.

Where they build: Malad West (1) · Goregaon West (1) · Bandra West (1)

Under construction

ProjectVillageStagePossessionBooked
Narang CastellaBandra WestEarly stageMarch 20320 units booked out of 24 units for sale
Narang ValoraGoregaon WestEarly stageDecember 203139 units booked out of 241 units for sale
Narang VivendaMalad WestNearing possessionDecember 2029165 units booked out of total 254 units

Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.

Is a project grouped wrongly or a figure out of date? Tell us