Narang Valora, Goregaon West

by Narang Realty Private Limited · Goregaon West, Mumbai 400104 · Map

Launched
May 20265 yrs 7 mths promised
Possession (MahaRERA)
Dec 2031Not extended
Concrete structure
0%Early stage
Booked (free sale)
39 of 24116% · 252 rehab units
Buildings
22.7 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale39 booked out of 241 units

Rehab252 units for existing members

Total 493 units. Rehab units are not for sale.

Project facts

2 BHK
100
3 BHK
358
4 BHK
35
Total units
493
Buildings
2
Land
2.7 acres
Phases
1
MahaRERA complaints
0
Free-sale units
241
Rehab units
252

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation88%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 0%Oct 2026: Excavation 88%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 88%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
88%0%0%39
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Narang Valora by Narang Realty Private Limited is a 493-unit BMC-sanctioned project in Goregaon West, Mumbai 400104, launched in May 2026 with possession due in December 2031. 39 units booked out of 241 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Narang Valora is a BMC-sanctioned project by Narang Realty Private Limited in Goregaon West, Mumbai 400104, registered with MahaRERA as PR1180002600544. It was launched in May 2026. It has 493 units in 2 buildings, with 2, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 493 units, 241 are for sale and 252 are rehab units for existing members.

Its registered possession date is December 2031, unchanged since launch. Construction: excavation 88% complete, structure (RCC) not started, final finishes not started.

39 units booked out of 241 units for sale (16%). Since the July 2026 update, 39 more units have been booked.

Narang Realty's track record in Mumbai

MahaRERA projects registered 2024–2026 in Mumbai

Projects registered with MahaRERA3
Total units across these projects792
Completed without extending the possession date0
Completed after an extension0
Lapsed0
Under construction3
Possession date extended on the builder's application0
MahaRERA complaints (filed by or against the builder), all Narang Realty projects0 (0 of 3 projects)

See all Narang Realty projects →