Oberoi Realty projects in Mumbai

MahaRERA projects by Oberoi Realty registered 2017–2026 in Mumbai.

Projects registered with MahaRERA9
Total units across these projects4,471
Full record

MahaRERA projects registered 2017–2026 in Mumbai

Completed without extending the possession date3
Completed after an extension1
Lapsed1
Under construction4
Possession date extended on the builder's application2
Typical time from launch to 100% structure7 years 4 months
MahaRERA complaints (filed by or against the builder), all Oberoi Realty projects41 (5 of 9 projects)
What these mean
  • Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
  • Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
  • Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
  • Under construction: MahaRERA status Active.
  • Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
  • Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
  • MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.

Where they build: Mulund West (2) · Jogeshwari East (2) · Goregaon East (2) · Bandra West (1)

Under construction

ProjectVillageStagePossessionBooked
Elysian · 3 phasesGoregaon EastMid-constructionJun 2027 – Oct 2031940 units booked out of total 1,266 units
OceanicBandra WestEarly stageDecember 20303 units booked out of 15 units for sale
Completed
ProjectVillageStatus
EnigmaMulund WestCompleted
EsquireGoregaon EastCompleted
MaximaJogeshwari EastCompleted
PrismaJogeshwari EastCompleted
Lapsed
ProjectVillageStatus
EterniaMulund WestLapsed

Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.