Elysian, Goregaon East
by Oberoi Realty Limited · Goregaon East, Mumbai 400063 · Map
- Launched
- Dec 2020First of 3 phases
- Possession (MahaRERA)
- Jun 2027 – Oct 2031Not extended
- Concrete structure
- 84%Weighted across 3 phases
- Booked
- 940 of 1,26674% · 887 in Jul 2026
- Buildings
- 551.7 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 3 BHK
- 734
- 4 BHK
- 522
- Other units
- 10
- Total units
- 1,266
- Buildings
- 5
- Land
- 51.7 acres
- Phases
- 3
- MahaRERA complaints
- 0
The 3 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Elysian Tower A Nearing possession | P51800027667 | 335 | 100% | 95% | |
| Elysian Tower B Nearing possession | P51800031456 | 340 | 100% | 85% | |
| Elysian Tower C, D, E Mid-construction | P51800050677 | 581 | 65% | 56% |
Show updates by phase
Elysian Tower A (P51800027667)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 30% | 320 | |
| 100% | 100% | 14% | 318 | |
| 100% | 100% | 6% | 312 | |
| 100% | 93% | 2% | 312 |
"–" means MahaRERA shows no figure for that update.
Elysian Tower B (P51800031456)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 26% | 290 | |
| 100% | 100% | 9% | 267 | |
| 100% | 89% | 4% | 247 | |
| 100% | 66% | 2% | 220 |
"–" means MahaRERA shows no figure for that update.
Elysian Tower C, D, E (P51800050677)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 99% | 65% | 4% | 330 | |
| 99% | 57% | 1% | 302 | |
| 89% | 45% | 0% | 258 | |
| 77% | 42% | 0% | 116 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
About this project
Elysian by Oberoi Realty Limited is a 1,266-unit BMC-sanctioned project in Goregaon East, Mumbai 400063, registered with MahaRERA in 3 phases, with possession dates from June 2027 to October 2031. 940 units booked out of total 1,266 units. The concrete structure (RCC) is 84% complete.
Read full summary
Elysian is a BMC-sanctioned project by Oberoi Realty Limited in Goregaon East, Mumbai 400063, registered with MahaRERA as 3 phases (P51800027667, P51800031456, P51800050677). The first phase was launched in December 2020. Together the phases have 1,266 units in 5 buildings: 1,256 homes (3 and 4 BHK) and 10 other units (shops, offices or not given by type), as registered with MahaRERA. All 3 phases are active on MahaRERA.
The phases' registered possession dates run from June 2027 to October 2031; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 84% complete and final finishes 17% complete. 2 of the 3 phases have their structure complete.
940 units booked out of total 1,266 units (74%). Since the July 2026 update, 53 more units have been booked.
Oberoi Realty's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 9 |
|---|---|
| Total units across these projects | 4,471 |
| Completed without extending the possession date | 3 |
| Completed after an extension | 1 |
| Lapsed | 1 |
| Under construction | 4 |
| Possession date extended on the builder's application | 2 |
| Typical time from launch to 100% structure | 7 years 4 months |
| MahaRERA complaints (filed by or against the builder), all Oberoi Realty projects | 41 (5 of 9 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.