Skip to main content

Elysian, Goregaon East

by Oberoi Realty Limited · Goregaon East, Mumbai 400063 · Map

Launched
Dec 2020First of 3 phases
Possession (MahaRERA)
Jun 2027 – Oct 2031Not extended
Concrete structure
84%Weighted across 3 phases
Booked
940 of 1,26674% · 887 in Jul 2026
Buildings
551.7 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

3 BHK
734
4 BHK
522
Other units
10
Total units
1,266
Buildings
5
Land
51.7 acres
Phases
3
MahaRERA complaints
0

The 3 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Elysian Tower A
Nearing possession
P51800027667335100%95%
Elysian Tower B
Nearing possession
P51800031456340100%85%
Elysian Tower C, D, E
Mid-construction
P5180005067758165%56%
Show updates by phase

Elysian Tower A (P51800027667)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%30%320
100%100%14%318
100%100%6%312
100%93%2%312

"–" means MahaRERA shows no figure for that update.

Elysian Tower B (P51800031456)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%26%290
100%100%9%267
100%89%4%247
100%66%2%220

"–" means MahaRERA shows no figure for that update.

Elysian Tower C, D, E (P51800050677)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
99%65%4%330
99%57%1%302
89%45%0%258
77%42%0%116

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)84%
Finishes, lifts and services17%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 89%Dec 2025: Excavation 95%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 62%Dec 2025: Concrete structure (RCC) 72%Jul 2026: Concrete structure (RCC) 80%Oct 2026: Concrete structure (RCC) 84%Dec 2024: Final finishes 1%Dec 2025: Final finishes 3%Jul 2026: Final finishes 7%Oct 2026: Final finishes 17%Excavation 100%Concrete structure (RCC) 84%Final finishes 17%

How to read construction stages

About this project

Elysian by Oberoi Realty Limited is a 1,266-unit BMC-sanctioned project in Goregaon East, Mumbai 400063, registered with MahaRERA in 3 phases, with possession dates from June 2027 to October 2031. 940 units booked out of total 1,266 units. The concrete structure (RCC) is 84% complete.

Read full summary

Elysian is a BMC-sanctioned project by Oberoi Realty Limited in Goregaon East, Mumbai 400063, registered with MahaRERA as 3 phases (P51800027667, P51800031456, P51800050677). The first phase was launched in December 2020. Together the phases have 1,266 units in 5 buildings: 1,256 homes (3 and 4 BHK) and 10 other units (shops, offices or not given by type), as registered with MahaRERA. All 3 phases are active on MahaRERA.

The phases' registered possession dates run from June 2027 to October 2031; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 84% complete and final finishes 17% complete. 2 of the 3 phases have their structure complete.

940 units booked out of total 1,266 units (74%). Since the July 2026 update, 53 more units have been booked.

Oberoi Realty's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA9
Total units across these projects4,471
Completed without extending the possession date3
Completed after an extension1
Lapsed1
Under construction4
Possession date extended on the builder's application2
Typical time from launch to 100% structure7 years 4 months
MahaRERA complaints (filed by or against the builder), all Oberoi Realty projects41 (5 of 9 projects)

See all Oberoi Realty projects →