Raheja Universal projects in Mumbai

MahaRERA projects by Raheja Universal registered 2017–2026 in Mumbai.

Projects registered with MahaRERA7
Total units across these projects1,254
Full record

MahaRERA projects registered 2017–2026 in Mumbai

Completed without extending the possession date1
Completed after an extension0
Lapsed0
Under construction6
Possession date extended on the builder's application1
Typical time from launch to 100% structure7 years 4 months
MahaRERA complaints (filed by or against the builder), all Raheja Universal projects8 (2 of 7 projects)
What these mean
  • Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
  • Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
  • Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
  • Under construction: MahaRERA status Active.
  • Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
  • Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
  • MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.

Where they build: Versova (5) · Lower Parel (1)

Under construction

ProjectVillageStagePossessionBooked
Raheja Exotica CyprusVersovaMid-constructionDecember 2029216 units booked out of total 266 units
Raheja Exotica DowntownVersovaEarly stageDecember 20260 units booked out of total 7 units
Raheja Exotica PositanoVersovaEarly stageJuly 2033–
Raheja Exotica SienaVersovaNearing possessionDecember 2028394 units booked out of total 394 units
Raheja Exotica VeronaVersovaNearing possessionDecember 2028131 units booked out of total 136 units
Raheja Imperia · 2 phasesLower ParelMid-constructionDec 2029–

Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.

Is a project grouped wrongly or a figure out of date? Tell us