Raheja Exotica Verona, Versova
by Raheja Universal (Pvt) Ltd · Versova, Mumbai 400061 · Map
- Launched
- Sep 20188 yrs 3 mths originally promised
- Possession (MahaRERA)
- Dec 2028Extended by 2 yrs
- Concrete structure
- 100%Nearing possession
- Booked
- 131 of 13696% · 121 in Jul 2026
- Buildings
- 10.2 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 71
- 3 BHK
- 30
- 4 BHK
- 35
- Total units
- 136
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 1
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 15% | 131 | |
| 100% | 90% | 0% | 121 | |
| 100% | 65% | 0% | 121 | |
| 100% | 45% | 0% | 116 |
"–" means MahaRERA shows no figure for that update.
About this project
Raheja Exotica Verona by Raheja Universal (Pvt) Ltd is a 136-unit BMC-sanctioned project in Versova, Mumbai 400061, launched in September 2018 with possession due in December 2028. 131 units booked out of total 136 units. The concrete structure (RCC) is complete.
Read full summary
Raheja Exotica Verona is a BMC-sanctioned project by Raheja Universal (Pvt) Ltd in Versova, Mumbai 400061, registered with MahaRERA as P51800017918. It was launched in September 2018. It has 136 units in 1 building, with 2, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2028, extended by 2 years from the original December 2026. Construction: excavation complete, structure (RCC) complete, final finishes 15% complete.
131 units booked out of total 136 units (96%). Since the July 2026 update, 10 more units have been booked and the reported concrete structure (RCC) has gone from 90% to 100%.
Raheja Universal's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 7 |
|---|---|
| Total units across these projects | 1,254 |
| Completed without extending the possession date | 1 |
| Completed after an extension | 0 |
| Lapsed | 0 |
| Under construction | 6 |
| Possession date extended on the builder's application | 1 |
| Typical time from launch to 100% structure | 7 years 4 months |
| MahaRERA complaints (filed by or against the builder), all Raheja Universal projects | 8 (2 of 7 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.