Sunteck projects in Mumbai
MahaRERA projects by Sunteck registered 2017–2021 in Mumbai.
| Projects registered with MahaRERA | 10 |
|---|---|
| Total units across these projects | 2,158 |
Full record
MahaRERA projects registered 2017–2021 in Mumbai
| Completed without extending the possession date | 5 |
|---|---|
| Completed after an extension | 3 |
| Lapsed | 0 |
| Under construction | 2 |
| Possession date extended on the builder's application | 5 |
| Typical time from launch to 100% structure | 6 years 1 month |
| MahaRERA complaints (filed by or against the builder), all Sunteck projects | 107 (7 of 10 projects) |
What these mean
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.
Where they build: Goregaon West (3) · Borivali East (1) · Andheri West (1) · Santacruz East (1) · Andheri East (1) · Kurla West (1)
Under construction
| Project | Village | Stage | Possession | Booked |
|---|---|---|---|---|
| 4TH AVENUE Sunteck City, ODC, Goregaon West | Goregaon West | Mid-construction | December 2028 | 533 units booked out of total 674 units |
| Sunteck Pinnacle · 2 phases | Goregaon West | Nearing possession | Dec 2027 | – |
Completed
| Project | Village | Status |
|---|---|---|
| Redevelopment of MCGB Staff Gilbird CHSL, Gilbird Hill Road, Andheri West | Andheri West | Completed |
| Signia High, Magathane, Western Express Highway, Borivali East | Borivali East | Completed |
| Sunteck BKC51 | Kurla West | Completed |
| Sunteck City Avenue | Goregaon West | Completed |
| Sunteck Crest | Andheri East | Completed |
| Sunteck Icon, Kolekalyan, CST Road, Kalina, Santacruz East, Mumbai | Santacruz East | Completed |
Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.
Is a project grouped wrongly or a figure out of date? Tell us