Sunteck Pinnacle, Goregaon West
by Sunteck Realty Limited · Goregaon West, Mumbai 400104 · Map
- Launched
- Mar 2021First of 2 phases
- Possession (MahaRERA)
- Dec 2027Extended in 1 of 2 phases
- Concrete structure
- 100%Weighted across 2 phases
- Booked
- –
- Buildings
- 20.5 acres
- MahaRERA complaints
- 4Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- Other units
- 131
- Total units
- 131
- Buildings
- 2
- Land
- 0.5 acres
- Phases
- 2
- MahaRERA complaints
- 4
- Reserved units
- 12
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Sunteck Pinnacle Completed | P51800028821 | 0 | 100% | – | |
| Sunteck Pinnacle 1 Nearing possession | P51800030947 | 0 | 100% | 80% |
Show updates by phase
Sunteck Pinnacle (P51800028821)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | – | |
| 100% | 100% | 100% | – | |
| 100% | 100% | 100% | 4 |
"–" means MahaRERA shows no figure for that update.
Sunteck Pinnacle 1 (P51800030947)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 77% | 101 | |
| 100% | 100% | 65% | 101 | |
| 100% | 100% | 20% | – | |
| 100% | 93% | 20% | 48 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
About this project
Sunteck Pinnacle by Sunteck Realty Limited is a 131-unit MMRDA-sanctioned project in Goregaon West, Mumbai 400104, registered with MahaRERA in 2 phases, with possession due in December 2027. The concrete structure (RCC) is complete.
Read full summary
Sunteck Pinnacle is an MMRDA-sanctioned project by Sunteck Realty Limited in Goregaon West, Mumbai 400104, registered with MahaRERA as 2 phases (P51800028821, P51800030947). The first phase was launched in March 2021. Together the phases have 131 units in 2 buildings, as registered with MahaRERA. On MahaRERA, 1 is completed and 1 is active.
The registered possession date is December 2027; 1 of 2 phases has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 78% complete. Both phases have their structure complete.
Sunteck's track record in Mumbai
MahaRERA projects registered 2017–2021 in Mumbai
| Projects registered with MahaRERA | 10 |
|---|---|
| Total units across these projects | 2,158 |
| Completed without extending the possession date | 5 |
| Completed after an extension | 3 |
| Lapsed | 0 |
| Under construction | 2 |
| Possession date extended on the builder's application | 5 |
| Typical time from launch to 100% structure | 6 years 1 month |
| MahaRERA complaints (filed by or against the builder), all Sunteck projects | 107 (7 of 10 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.