Tungwa Powai, Powai

Lapsed

by Mhada · Powai, Mumbai 400076 · Map

Launched
Jun 20179 mths originally promised
Possession (MahaRERA)
Mar 2019Extended by 1 yrWhat does Lapsed mean?
Concrete structure
98%Mid-construction
Booked
–
Buildings
59.7 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
933
2 BHK
252
Other units
6
Total units
1,191
Buildings
5
Land
9.7 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)98%
Finishes, lifts and services93%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 98%Dec 2025: Concrete structure (RCC) 98%Jul 2026: Concrete structure (RCC) 98%Dec 2024: Final finishes 93%Dec 2025: Final finishes 93%Jul 2026: Final finishes 93%Excavation 100%Concrete structure (RCC) 98%Final finishes 93%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%98%93%–
100%98%93%–
100%98%93%933

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Tungwa Powai by Mhada is a 1,191-unit project in Powai, Mumbai 400076, launched in June 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is 98% complete.

Read full summary

Tungwa Powai is a project by Mhada in Powai, Mumbai 400076, registered with MahaRERA as P51800000056. It was launched in June 2017. It has 1,191 units in 5 buildings: 1,185 homes (1 and 2 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in March 2019, after an extension of 1 year from the original March 2018. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 98% complete, final finishes 93% complete.