- Launched
- Jul 20173 yrs 11 mths originally promised
- Possession (MahaRERA)
- Dec 2023Extended by 2 yrs 6 mthsWhat does Lapsed mean?
- Concrete structure
- 0%Early stage
- Booked
- –
- Buildings
- 10.5 acres
- MahaRERA complaints
- 48Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 1
- Total units
- 1
- Buildings
- 1
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 48
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | 50 | |
| 100% | 0% | 0% | – | |
| 100% | 0% | 0% | – | |
| 100% | 0% | 0% | 50 |
"–" means MahaRERA shows no figure for that update.
About this project
Mirabilis by Skylink Hospitality LLP is a 1-unit SRA-sanctioned project in Santacruz East, Mumbai 400055, launched in July 2017; its MahaRERA registration has lapsed. Work on the concrete structure (RCC) has not started.
Read full summary
Mirabilis is an SRA-sanctioned project by Skylink Hospitality LLP in Santacruz East, Mumbai 400055, registered with MahaRERA as P51800000370. It was launched in July 2017. It has 1 unit in 1 building, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2023, after an extension of 2 years 6 months from the original June 2021. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) not started, final finishes not started.
Since the July 2026 update, the possession date has moved from June 2023 to December 2023.