Hillcrest, Andheri East

Lapsed

by Hillcrest Joint Venture · Andheri East, Mumbai 400093 · Map

Launched
Jul 2017First of 3 phases
Possession (MahaRERA)
Dec 2022Not extendedWhat does Lapsed mean?
Concrete structure
100%Weighted across 3 phases
Booked
–
Buildings
30.5 acres
MahaRERA complaints
7Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
130
3 BHK
73
Total units
203
Buildings
3
Land
0.5 acres
Phases
3
MahaRERA complaints
7

The 3 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Hillcrest C Wing
Ready to move Lapsed
P518000004930100%–
Hillcrest B Wing
Completed
P5180000050873100%–
Hillcrest A Wing
Completed
P51800002556130100%–
Show updates by phase

Hillcrest C Wing (P51800000493)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%–
100%100%100%–
100%100%100%69

"–" means MahaRERA shows no figure for that update.

Hillcrest B Wing (P51800000508)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%–
100%100%100%–
100%100%100%54

"–" means MahaRERA shows no figure for that update.

Hillcrest A Wing (P51800002556)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%74%–
100%100%74%–
100%100%74%121

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services83%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 83%Dec 2025: Final finishes 83%Jul 2026: Final finishes 83%Excavation 100%Concrete structure (RCC) 100%Final finishes 83%

How to read construction stages

About this project

Hillcrest by Hillcrest Joint Venture is a 203-unit project in Andheri East, Mumbai 400093, registered with MahaRERA in 3 phases, with possession due in December 2022. The concrete structure (RCC) is complete.

Read full summary

Hillcrest is a project by Hillcrest Joint Venture in Andheri East, Mumbai 400093, registered with MahaRERA as 3 phases (P51800000493, P51800000508, P51800002556). The first phase was launched in July 2017. Together the phases have 203 units in 3 buildings, with 2 and 3 BHK homes as registered with MahaRERA. On MahaRERA, 2 are completed and 1 is lapsed.

The registered possession date is December 2022; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 83% complete. All 3 phases have their structure complete.