Vinayak Heights Phase 1, Ghatkopar East
Ready to moveLapsed
by Vinayak Associate · Ghatkopar East, Mumbai 400075 · Map
- Launched
- Jul 20173 yrs 5 mths originally promised
- Possession (MahaRERA)
- Dec 2021Extended by 1 yrWhat does Lapsed mean?
- Concrete structure
- 100%Ready to move
- Booked
- –
- Buildings
- 10.7 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 124
- Other units
- 14
- Total units
- 138
- Buildings
- 1
- Land
- 0.7 acres
- Phases
- 1
- MahaRERA complaints
- 1
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 90% | – | |
| 100% | 100% | 90% | – | |
| 100% | 100% | 90% | 81 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400075
Projects with 60–250 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 5 mths | 5 yrs 10 mths |
| Possession date extended | By 1 yr | 3 of 3 |
| Possession date (MahaRERA) | Dec 2021 | Dec 2027 |
| Concrete structure (RCC) | 100% | 70% |
| Units booked | – | 72% |
| MahaRERA complaints (filed by or against the builder) | 1 | 1 |
The 3 projects
- Odhav K K Residency, Ghatkopar East
- Pant Nagar Ganadhiraj CHSL, Ghatkopar East
- Sofrance, Ghatkopar East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Odhav K K Residency | July 2017 | March 2028 | 100% | 40 units booked out of 45 units for sale |
| Pant Nagar Ganadhiraj CHSL | August 2017 | December 2027 | 70% | 41 units booked out of 57 units for sale |
| Sofrance | August 2017 | Dec 2022 – Apr 2028 | 12% | 38 units booked out of total 80 units |
About this project
Vinayak Heights Phase 1 by Vinayak Associate is a 138-unit project in Ghatkopar East, Mumbai 400075, launched in July 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is complete.
Read full summary
Vinayak Heights Phase 1 is a project by Vinayak Associate in Ghatkopar East, Mumbai 400075, registered with MahaRERA as P51800000626. It was launched in July 2017. It has 138 units in 1 building: 124 homes (1 BHK) and 14 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2021, after an extension of 1 year from the original December 2020. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.