Yellow Roses, Borivali West

Ready to moveLapsed

by Navkar Infra Projects · Borivali West, Mumbai 400103 · Map

Launched
Jul 20173 yrs originally promised
Possession (MahaRERA)
Dec 2024Extended by 4 yrs 5 mthsWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked
24 of 24100%
Buildings
1
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
1
2 BHK
11
Other units
12
Total units
24
Buildings
1
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services95%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 95%Dec 2025: Final finishes 95%Jul 2026: Final finishes 95%Oct 2026: Final finishes 95%Excavation 100%Concrete structure (RCC) 100%Final finishes 95%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%95%24
100%100%95%–
100%100%95%–
100%100%95%24

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Yellow Roses by Navkar Infra Projects is a 24-unit BMC-sanctioned project in Borivali West, Mumbai 400103, launched in July 2017; its MahaRERA registration has lapsed. 24 units booked out of total 24 units. The concrete structure (RCC) is complete.

Read full summary

Yellow Roses is a BMC-sanctioned project by Navkar Infra Projects in Borivali West, Mumbai 400103, registered with MahaRERA as P51800000712. It was launched in July 2017. It has 24 units in 1 building: 12 homes (1 RK and 2 BHK) and 12 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2024, after an extension of 4 years 5 months from the original July 2020. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

24 units booked out of total 24 units (100%).