Altavista, Chembur
by Spenta Enclave Private Limited · Chembur, Mumbai 400071 · Map
- Launched
- Jul 2017First of 4 phases
- Possession (MahaRERA)
- Jun 2028 – Dec 2029Extended in all 4 phases
- Concrete structure
- 84%Weighted across 4 phases
- Booked
- –
- Buildings
- 81.4 acres
- MahaRERA complaints
- 31Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 130
- 2 BHK
- 372
- 3 BHK
- 199
- Total units
- 701
- Buildings
- 8
- Land
- 1.4 acres
- Phases
- 4
- MahaRERA complaints
- 31
The 4 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Altavista - Phase 1 Completed | P51800001050 | 355 | 100% | – | |
| Altavista - Phase 2 Nearing possession | P51800000956 | 169 | 100% | 92% | |
| Altavista - Phase 3 Nearing possession | P51800021249 | 64 | 100% | 55% | |
| Altavista - Phase 4 Early stage | P51800026131 | 113 | 0% | 17% |
Show updates by phase
Altavista - Phase 1 (P51800001050)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | – | |
| 100% | 100% | 100% | – | |
| 100% | 100% | 100% | 353 |
"–" means MahaRERA shows no figure for that update.
Altavista - Phase 2 (P51800000956)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 38% | 156 | |
| 100% | 100% | 38% | 156 | |
| 100% | 83% | 0% | 156 | |
| 100% | 83% | 0% | 156 |
"–" means MahaRERA shows no figure for that update.
Altavista - Phase 3 (P51800021249)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | 35 | |
| 100% | 92% | 0% | 35 | |
| 100% | 0% | 0% | 35 | |
| 100% | 0% | 0% | 34 |
"–" means MahaRERA shows no figure for that update.
Altavista - Phase 4 (P51800026131)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | 19 | |
| 100% | 0% | 0% | 19 | |
| 98% | 0% | 0% | 19 | |
| 98% | 0% | 0% | 18 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
About this project
Altavista by Spenta Enclave Private Limited is a 701-unit SRA-sanctioned project in Chembur, Mumbai 400071, registered with MahaRERA in 4 phases, with possession dates from June 2028 to December 2029. The concrete structure (RCC) is 84% complete.
Read full summary
Altavista is an SRA-sanctioned project by Spenta Enclave Private Limited in Chembur, Mumbai 400071, registered with MahaRERA as 4 phases (P51800000956, P51800001050, P51800021249, P51800026131). The first phase was launched in July 2017. Together the phases have 701 units in 8 buildings, with 1, 2 and 3 BHK homes as registered with MahaRERA. On MahaRERA, 3 are active and 1 is completed.
The phases' registered possession dates run from June 2028 to December 2029; all 4 phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 84% complete and final finishes 60% complete. 3 of the 4 phases have their structure complete.
Spenta's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 10 |
|---|---|
| Total units across these projects | 1,369 |
| Completed without extending the possession date | 1 |
| Completed after an extension | 2 |
| Lapsed | 0 |
| Under construction | 7 |
| Possession date extended on the builder's application | 7 |
| Typical time from launch to 100% structure | 7 years 5 months |
| MahaRERA complaints (filed by or against the builder), all Spenta projects | 43 (6 of 10 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.