Spenta projects in Mumbai
MahaRERA projects by Spenta registered 2017–2026 in Mumbai.
| Projects registered with MahaRERA | 10 |
|---|---|
| Total units across these projects | 1,369 |
Full record
MahaRERA projects registered 2017–2026 in Mumbai
| Completed without extending the possession date | 1 |
|---|---|
| Completed after an extension | 2 |
| Lapsed | 0 |
| Under construction | 7 |
| Possession date extended on the builder's application | 7 |
| Typical time from launch to 100% structure | 7 years 5 months |
| MahaRERA complaints (filed by or against the builder), all Spenta projects | 43 (6 of 10 projects) |
What these mean
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.
Where they build: Chembur (3) · Khar West (1) · Chandivali (1) · Dadar East (1) · Andheri West (1)
Under construction
| Project | Village | Stage | Possession | Booked |
|---|---|---|---|---|
| Altavista · 4 phases | Chembur | Mid-construction | Jun 2028 – Dec 2029 | – |
| Ornata - Amber | Chembur | Early stage | December 2029 | 20 units booked out of total 202 units |
| Ornata - Sapphire | Chembur | Early stage | June 2028 | 100 units booked out of total 202 units |
| Spenta Anthea | Andheri West | Early stage | December 2029 | 129 units booked out of 154 units for sale |
| Spenta Nest | Dadar East | Nearing possession | December 2028 | – |
Completed
| Project | Village | Status |
|---|---|---|
| Palazzio | Chandivali | Completed |
| Spenta | Khar West | Completed |
Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.
Is a project grouped wrongly or a figure out of date? Tell us