Runwal Forests, Bhandup West
by Wheelabrator Alloy Castings Limited · Bhandup West, Mumbai 400078 · Map
- Launched
- Jul 2017First of 2 phases
- Possession (MahaRERA)
- Jun 2027Extended in 1 of 2 phases
- Concrete structure
- 100%Weighted across 2 phases
- Booked
- –
- Buildings
- 715.5 acres
- MahaRERA complaints
- 69Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 108
- 2 BHK
- 1,183
- 3 BHK
- 382
- Total units
- 1,673
- Buildings
- 7
- Land
- 15.5 acres
- Phases
- 2
- MahaRERA complaints
- 69
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Runwal Forests Tower 9 - 11 Nearing possession | P51800001137 | 1,047 | 100% | 97% | |
| Runwal Forests Tower 5-8 Completed | P51800001838 | 626 | 100% | – |
Show updates by phase
Runwal Forests Tower 9 - 11 (P51800001137)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 82% | 1,016 | |
| 100% | 99% | 65% | 1,016 | |
| 100% | 89% | 55% | – | |
| 100% | 89% | 34% | 941 |
"–" means MahaRERA shows no figure for that update.
Runwal Forests Tower 5-8 (P51800001838)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | – | |
| 100% | 100% | 100% | – | |
| 100% | 100% | 100% | 619 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
About this project
Runwal Forests by Wheelabrator Alloy Castings Limited (Runwal) is a 1,673-unit project in Bhandup West, Mumbai 400078, registered with MahaRERA in 2 phases, with possession due in June 2027. The concrete structure (RCC) is complete.
Read full summary
Runwal Forests is a project by Wheelabrator Alloy Castings Limited in Bhandup West, Mumbai 400078, registered with MahaRERA as 2 phases (P51800001137, P51800001838). The first phase was launched in July 2017. Together the phases have 1,673 units in 7 buildings, with 1, 2 and 3 BHK homes as registered with MahaRERA. On MahaRERA, 1 is active and 1 is completed.
The registered possession date is June 2027; 1 of 2 phases has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 89% complete. Both phases have their structure complete.
Runwal's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 46 |
|---|---|
| Total units across these projects | 14,623 |
| Completed without extending the possession date | 10 |
| Completed after an extension | 5 |
| Lapsed | 5 |
| Under construction | 26 |
| Possession date extended on the builder's application | 16 |
| Typical time from launch to 100% structure | 7 years 4 months |
| MahaRERA complaints (filed by or against the builder), all Runwal projects | 343 (35 of 46 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.