Runwal projects in Mumbai
MahaRERA projects by Runwal registered 2017–2026 in Mumbai.
| Projects registered with MahaRERA | 46 |
|---|---|
| Total units across these projects | 14,623 |
Full record
MahaRERA projects registered 2017–2026 in Mumbai
| Completed without extending the possession date | 10 |
|---|---|
| Completed after an extension | 5 |
| Lapsed | 5 |
| Under construction | 26 |
| Possession date extended on the builder's application | 16 |
| Typical time from launch to 100% structure | 7 years 4 months |
| MahaRERA complaints (filed by or against the builder), all Runwal projects | 343 (35 of 46 projects) |
What these mean
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.
Where they build: Bhandup East (5) · Mulund West (4) · Sion (2) · Bhandup West (2) · Malabar Hill (2) · Lower Parel (2) · Chandivali (1) · Mankhurd (1) · Jogeshwari West (1) · Andheri West (1)
Under construction
| Project | Village | Stage | Possession | Booked |
|---|---|---|---|---|
| 7 Mahalaxmi · 2 phases | Lower Parel | Early stage | Oct 2031 – Sep 2034 | 134 units booked out of total 639 units |
| 7 Mahalaxmi - Tower 2 | Mahalaxmi | Early stage | October 2031 | 49 units booked out of total 150 units |
| Runwal Avenue · 6 phases | Bhandup East | Mid-construction | Jun 2027 – Feb 2029 | 1,344 units booked out of total 1,927 units |
| Runwal Bliss · 8 phases | Bhandup East | Mid-construction | Dec 2027 – Nov 2029 | – |
| Runwal Forests · 2 phases | Bhandup West | Nearing possession | Jun 2027 | – |
| Runwal Malabar | Malabar Hill | Early stage | June 2032 | 1 unit booked out of 2 units for sale |
| Runwal Meadows-Aster | Bhandup East | Early stage | July 2033 | 183 units booked out of total 245 units |
| Runwal Meadows-Daisy | Bhandup East | Early stage | July 2033 | 0 units booked out of total 461 units |
| Runwal Nexus | Malad West | Early stage | December 2026 | 12 units booked out of total 25 units |
| Runwal Pinnacle | Mulund West | Mid-construction | December 2028 | 650 units booked out of total 1,107 units |
| Runwal Raaya · 2 phases | Lower Parel | Early stage | Dec 2032 | 76 units booked out of total 419 units |
| Runwal Timeless | Sion | Mid-construction | January 2029 | 540 units booked out of total 749 units |
| Runwal Westwind Heights | Khar West | Mid-construction | December 2028 | 29 units booked out of 65 units for sale |
| Runwal Woods | Chembur | Early stage | November 2031 | 0 units booked out of total 422 units |
| The Sanctuary · 4 phases | Mulund West | Mid-construction | Jan 2027 – Mar 2027 | 891 units booked out of total 1,797 units |
Completed
| Project | Village | Status |
|---|---|---|
| Runwal Elegante | Jogeshwari West | Completed |
| Runwal Elina | Chandivali | Completed |
| Runwal Forest | Bhandup West | Completed |
| RUNWAL GREENS | Sion | Completed |
| Runwal Reserve | Worli | Completed |
| Runwal Serene | Mankhurd | Completed |
| The Residence | Malabar Hill | Completed |
Lapsed
| Project | Village | Status |
|---|---|---|
| Codename Rare By Runwal | Andheri West | Lapsed |
| Nirvana | Parel | Lapsed |
| Runwal Anthurium | Mulund West | Lapsed |
| Runwal Commerz | Bhandup East | Lapsed |
| Runwal R-Square | Mulund West | Lapsed |
Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.
Is a project grouped wrongly or a figure out of date? Tell us