Virmati Villa CHS Ltd, Borivali West
Lapsed
by Shamik Enterprises Pvt Ltd · Borivali West, Mumbai 400103 · Map
- Launched
- Jul 20171 yr 11 mths originally promised
- Possession (MahaRERA)
- Dec 2020Extended by 1 yr 6 mthsWhat does Lapsed mean?
- Concrete structure
- 100%Nearing possession
- Booked
- 14 of 14100%
- Buildings
- 10.1 acres
- MahaRERA complaints
- 5Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 1
- 2 BHK
- 1
- 3 BHK
- 12
- Total units
- 14
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 5
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | 14 | |
| 100% | 100% | 0% | – | |
| 100% | 100% | 0% | – | |
| 100% | 100% | 0% | 14 |
"–" means MahaRERA shows no figure for that update.
About this project
Virmati Villa CHS Ltd by Shamik Enterprises Pvt Ltd is a 14-unit project in Borivali West, Mumbai 400103, launched in July 2017; its MahaRERA registration has lapsed. 14 units booked out of total 14 units. The concrete structure (RCC) is complete.
Read full summary
Virmati Villa CHS Ltd is a project by Shamik Enterprises Pvt Ltd in Borivali West, Mumbai 400103, registered with MahaRERA as P51800001564. It was launched in July 2017. It has 14 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2020, after an extension of 1 year 6 months from the original June 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes not started.
14 units booked out of total 14 units (100%).