- Launched
- Jul 20171 yr 8 mths originally promised
- Possession (MahaRERA)
- Sep 2020Extended by 1 yr 6 mthsWhat does Lapsed mean?
- Concrete structure
- 50%Mid-construction
- Booked
- 6 of 2129%
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 20
- 2 BHK
- 1
- Total units
- 21
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 95% | 50% | 10% | 6 | |
| 95% | 50% | 10% | – | |
| 95% | 50% | 10% | – | |
| 95% | 50% | 10% | 6 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400057
Projects with 10–50 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 1 yr 8 mths | 1 yr 7 mths |
| Possession date extended | By 1 yr 6 mths | 3 of 3 |
| Possession date (MahaRERA) | Sep 2020 | Jun 2022 |
| Concrete structure (RCC) | 50% | 0% |
| Units booked | 29% | 84% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Paresh Kunj, Vile Parle East
- Swarup Niketan, Vile Parle East
- Ventures ALTA MONTE, Vile Parle East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Paresh Kunj | July 2017 | June 2022 | 0% | 15 units booked out of total 20 units |
| Swarup Niketan | July 2017 | February 2020 | 0% | 21 units booked out of total 25 units |
| Ventures ALTA MONTE | August 2017 | May 2026 | 50% | 12 units booked out of total 13 units |
About this project
Neumec Vinayak by Neumec Venture is a 21-unit project in Vile Parle East, Mumbai 400057, launched in July 2017; its MahaRERA registration has lapsed. 6 units booked out of total 21 units. The concrete structure (RCC) is 50% complete.
Read full summary
Neumec Vinayak is a project by Neumec Venture in Vile Parle East, Mumbai 400057, registered with MahaRERA as P51800001651. It was launched in July 2017. It has 21 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in September 2020, after an extension of 1 year 6 months from the original March 2019. That date has passed and no further extension has been recorded. Construction: excavation 95% complete, structure (RCC) 50% complete, final finishes 10% complete.
6 units booked out of total 21 units (29%).