Azure, Powai

Lapsed

by One Buildcon · Powai, Mumbai 400076 · Map

Launched
Jul 20172 yrs 5 mths originally promised
Possession (MahaRERA)
Dec 2020Extended by 1 yrWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
–
Buildings
10.3 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
40
Total units
40
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services80%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 80%Dec 2025: Final finishes 80%Jul 2026: Final finishes 80%Excavation 100%Concrete structure (RCC) 100%Final finishes 80%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%80%–
100%100%80%–
100%100%80%10

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Azure by One Buildcon is a 40-unit project in Powai, Mumbai 400076, launched in July 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is complete.

Read full summary

Azure is a project by One Buildcon in Powai, Mumbai 400076, registered with MahaRERA as P51800002018. It was launched in July 2017. It has 40 units in 1 building, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2020, after an extension of 1 year from the original December 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 80% complete.