- Launched
- Jul 20172 yrs 5 mths originally promised
- Possession (MahaRERA)
- Dec 2020Extended by 1 yrWhat does Lapsed mean?
- Concrete structure
- 100%Nearing possession
- Booked
- –
- Buildings
- 10.3 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 40
- Total units
- 40
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 1
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 80% | – | |
| 100% | 100% | 80% | – | |
| 100% | 100% | 80% | 10 |
"–" means MahaRERA shows no figure for that update.
About this project
Azure by One Buildcon is a 40-unit project in Powai, Mumbai 400076, launched in July 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is complete.
Read full summary
Azure is a project by One Buildcon in Powai, Mumbai 400076, registered with MahaRERA as P51800002018. It was launched in July 2017. It has 40 units in 1 building, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2020, after an extension of 1 year from the original December 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 80% complete.