Emerald Isle, Chandivali

by Larsen & Toubro Ltd. (Realty Division) · Chandivali, Mumbai 400072 · Map

Launched
Jul 2017First of 7 phases
Possession (MahaRERA)
Sep 2027Extended in 2 of 7 phases
Concrete structure
83%Weighted across 7 phases
Booked
–
Buildings
90.5 acres
MahaRERA complaints
65Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
127
2 BHK
480
3 BHK
376
4 BHK
50
Other units
2
Total units
1,035
Buildings
9
Land
0.5 acres
Phases
7
MahaRERA complaints
65

The 7 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Emerald Isle - T8
Completed
P5180000223072100%–
Emerald Isle - T4, T5, T6
Completed
P51800003307371100%–
Emerald Isle - T7
Completed
P5180000507272100%–
Emerald Isle - T9
Completed
P51800007280107––
Emerald Isle - T10
Completed
P51800013052138––
Emerald Isle - T15
Completed
P51800013214146––
Emerald Isle - T16
Mid-construction
P5180001350412767%91%
Show updates by phase

Emerald Isle - T8 (P51800002230)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%99%–
100%100%99%–
100%100%99%58

"–" means MahaRERA shows no figure for that update.

Emerald Isle - T4, T5, T6 (P51800003307)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%–
100%100%100%–
100%100%100%370

"–" means MahaRERA shows no figure for that update.

Emerald Isle - T7 (P51800005072)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%–
100%100%100%–
100%100%100%67

"–" means MahaRERA shows no figure for that update.

Emerald Isle - T9 (P51800007280)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%67%100%–
100%67%100%–
100%67%100%102

"–" means MahaRERA shows no figure for that update.

Emerald Isle - T10 (P51800013052)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%63%25%–
100%63%25%–
100%63%25%107

"–" means MahaRERA shows no figure for that update.

Emerald Isle - T15 (P51800013214)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%67%95%–
100%67%95%–
100%67%95%138

"–" means MahaRERA shows no figure for that update.

Emerald Isle - T16 (P51800013504)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%67%100%116
100%67%98%116
100%67%98%–
100%67%98%118

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)83%
Finishes, lifts and services89%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 83%Dec 2025: Concrete structure (RCC) 83%Jul 2026: Concrete structure (RCC) 83%Oct 2026: Concrete structure (RCC) 83%Dec 2024: Final finishes 89%Dec 2025: Final finishes 89%Jul 2026: Final finishes 89%Oct 2026: Final finishes 89%Excavation 100%Final finishes 89%Concrete structure (RCC) 83%

How to read construction stages

About this project

Emerald Isle by Larsen & Toubro Ltd. (Realty Division) (L&T Realty) is a 1,035-unit BMC-sanctioned project in Chandivali, Mumbai 400072, registered with MahaRERA in 7 phases, with possession due in September 2027. The concrete structure (RCC) is 83% complete.

Read full summary

Emerald Isle is a BMC-sanctioned project by Larsen & Toubro Ltd. (Realty Division) in Chandivali, Mumbai 400072, registered with MahaRERA as 7 phases (P51800002230, P51800003307, P51800005072, P51800007280, P51800013052, P51800013214, P51800013504). The first phase was launched in July 2017. Together the phases have 1,035 units in 9 buildings: 1,033 homes (1, 2, 3 and 4 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. On MahaRERA, 6 are completed and 1 is active.

The registered possession date is September 2027; 2 of 7 phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 83% complete and final finishes 89% complete. 3 of the 7 phases have their structure complete.

L&T Realty's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA29
Total units across these projects4,949
Completed without extending the possession date11
Completed after an extension3
Lapsed3
Under construction12
Possession date extended on the builder's application8
Typical time from launch to 100% structure4 years 5 months
MahaRERA complaints (filed by or against the builder), all L&T Realty projects114 (16 of 29 projects)