L&T Realty projects in Mumbai

MahaRERA projects by L&T Realty registered 2017–2026 in Mumbai.

Projects registered with MahaRERA29
Total units across these projects4,949
Full record

MahaRERA projects registered 2017–2026 in Mumbai

Completed without extending the possession date11
Completed after an extension3
Lapsed3
Under construction12
Possession date extended on the builder's application8
Typical time from launch to 100% structure4 years 5 months
MahaRERA complaints (filed by or against the builder), all L&T Realty projects114 (16 of 29 projects)
What these mean
  • Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
  • Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
  • Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
  • Under construction: MahaRERA status Active.
  • Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
  • Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
  • MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.

Where they build: Chandivali (10) · Parel (2) · Malad East (1) · Bandra East (1)

Under construction

ProjectVillageStagePossessionBooked
ATTHIS at L and T Realty Elixir ReserveChandivaliNearing possessionSeptember 2027165 units booked out of total 190 units
BARBET at L and T Realty Elixir ReserveChandivaliEarly stageJuly 2029167 units booked out of total 241 units
CYGNUS at L and T Realty Elixir ReserveChandivaliNearing possessionApril 202886 units booked out of total 121 units
DOVE at L and T Realty Elixir ReserveChandivaliNearing possessionAugust 2028103 units booked out of total 139 units
Emerald Isle · 7 phasesChandivaliMid-constructionSep 2027–
L&T Realty Ahana · 2 phasesMalad EastEarly stageJul 2032 – Jun 203396 units booked out of total 565 units
L&T Realty HarmonyBandra EastMid-constructionAugust 20280 units booked out of 31 units for sale
PRINIA at L and T Realty Elixir ReserveChandivaliMid-constructionJuly 2029106 units booked out of total 133 units
Veridian at Emerald Isle · 5 phasesChandivaliReady to moveApr 2025 – Sep 2027650 units booked out of total 684 units
Completed
ProjectVillageStatus
CAFER at L and T Realty Elixir ReserveChandivaliCompleted
Crescent BayParelCompleted
IBIS at L and T Realty Elixir ReserveChandivaliCompleted
Lapsed
ProjectVillageStatus
IORA at L and T Realty Elixir ReserveChandivaliLapsed

Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.

Is a project grouped wrongly or a figure out of date? Tell us