- Launched
- Jul 20172 yrs 2 mths originally promised
- Possession (MahaRERA)
- Mar 2025Extended by 5 yrs 6 mthsWhat does Lapsed mean?
- Concrete structure
- 35%Mid-construction
- Booked
- –
- Buildings
- 21.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- Total units
- –
- Buildings
- 2
- Land
- 1.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 35% | 0% | – | |
| 100% | 35% | 0% | – | |
| 100% | 35% | 0% | 123 |
"–" means MahaRERA shows no figure for that update.
About this project
Simran Heights by Vikas Narayan Raikar is a project in Chembur, Mumbai 400071, launched in July 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is 35% complete.
Read full summary
Simran Heights is a project by Vikas Narayan Raikar in Chembur, Mumbai 400071, registered with MahaRERA as P51800002238. It was launched in July 2017. Its MahaRERA status is Lapsed.
Possession was due in March 2025, after an extension of 5 years 6 months from the original September 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 35% complete, final finishes not started.