Siddharth Palace, Malad West

Lapsed

by Rajkumar Raghunath Kushwaha · Malad West, Mumbai 400064 · Map

Launched
Jul 20172 yrs 5 mths originally promised
Possession (MahaRERA)
Jun 2022Extended by 2 yrs 6 mthsWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
–
Buildings
10.2 acres
MahaRERA complaints
26Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
14
1 BHK
22
2 BHK
14
3 BHK
1
Other units
4
Total units
55
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
26

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services60%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 60%Dec 2025: Final finishes 60%Jul 2026: Final finishes 60%Excavation 100%Concrete structure (RCC) 100%Final finishes 60%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%60%–
100%100%60%–
100%100%60%47

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Siddharth Palace by Rajkumar Raghunath Kushwaha is a 55-unit project in Malad West, Mumbai 400064, launched in July 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is complete.

Read full summary

Siddharth Palace is a project by Rajkumar Raghunath Kushwaha in Malad West, Mumbai 400064, registered with MahaRERA as P51800002257. It was launched in July 2017. It has 55 units in 1 building: 51 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in June 2022, after an extension of 2 years 6 months from the original December 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 60% complete.