Jai Shubamkaroti, Andheri East
Ready to moveLapsed
by Sun-Vision Estates Ltd · Andheri East, Mumbai 400099 · Map
- Launched
- Jul 20175 mths promised
- Possession (MahaRERA)
- Dec 2017Not extendedWhat does Lapsed mean?
- Concrete structure
- 100%Ready to move
- Booked
- 13 of 13100%
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 12
- 3 BHK
- 1
- Total units
- 13
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 95% | 13 | |
| 100% | 100% | 95% | – | |
| 100% | 100% | 95% | – | |
| 100% | 100% | 95% | 13 |
"–" means MahaRERA shows no figure for that update.
About this project
Jai Shubamkaroti by Sun-Vision Estates Ltd is a 13-unit project in Andheri East, Mumbai 400099, launched in July 2017; its MahaRERA registration has lapsed. 13 units booked out of total 13 units. The concrete structure (RCC) is complete.
Read full summary
Jai Shubamkaroti is a project by Sun-Vision Estates Ltd in Andheri East, Mumbai 400099, registered with MahaRERA as P51800002366. It was launched in July 2017. It has 13 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2017. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
13 units booked out of total 13 units (100%).