Redevlopment of Govadhangiri, Goregaon West

Lapsed

by Taksha Spaces Private Limited · Goregaon West, Mumbai 400104 · Map

Launched
Aug 20175 yrs 2 mths promised
Possession (MahaRERA)
Oct 2022Not extendedWhat does Lapsed mean?
Concrete structure
64%Mid-construction
Booked
18 of 5533%
Buildings
21.1 acres
MahaRERA complaints
8Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

3 BHK
53
5+ BHK
2
Total units
55
Buildings
2
Land
1.1 acres
Phases
1
MahaRERA complaints
8

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation75%
Concrete structure (slabs)64%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 75%Dec 2025: Excavation 75%Jul 2026: Excavation 75%Oct 2026: Excavation 75%Dec 2024: Concrete structure (RCC) 64%Dec 2025: Concrete structure (RCC) 64%Jul 2026: Concrete structure (RCC) 64%Oct 2026: Concrete structure (RCC) 64%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 75%Concrete structure (RCC) 64%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
75%64%0%18
75%64%0%–
75%64%0%–
75%64%0%18

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Redevlopment of Govadhangiri by Taksha Spaces Private Limited is a 55-unit project in Goregaon West, Mumbai 400104, launched in August 2017; its MahaRERA registration has lapsed. 18 units booked out of total 55 units. The concrete structure (RCC) is 64% complete.

Read full summary

Redevlopment of Govadhangiri is a project by Taksha Spaces Private Limited in Goregaon West, Mumbai 400104, registered with MahaRERA as P51800002450. It was launched in August 2017. It has 55 units in 2 buildings, with 3 and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in October 2022. That date has passed and no extension has been recorded. Construction: excavation 75% complete, structure (RCC) 64% complete, final finishes not started.

18 units booked out of total 55 units (33%).