Vicinia, Chandivali

Lapsed

by Forbes & Company Limited · Chandivali, Mumbai 400072 · Map

Launched
Aug 20174 yrs 10 mths originally promised
Possession (MahaRERA)
Jun 2023Extended by 1 yrWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
–
Buildings
86.7 acres
MahaRERA complaints
58Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
588
Total units
588
Buildings
8
Land
6.7 acres
Phases
1
MahaRERA complaints
58

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services72%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 72%Dec 2025: Final finishes 72%Jul 2026: Final finishes 72%Excavation 100%Concrete structure (RCC) 100%Final finishes 72%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%72%–
100%100%72%–
100%100%72%575

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Vicinia by Forbes & Company Limited is a 588-unit project in Chandivali, Mumbai 400072, launched in August 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is complete.

Read full summary

Vicinia is a project by Forbes & Company Limited in Chandivali, Mumbai 400072, registered with MahaRERA as P51800002564. It was launched in August 2017. It has 588 units in 8 buildings, as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in June 2023, after an extension of 1 year from the original June 2022. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 72% complete.