Happy Home Chsl, Borivali West
Ready to moveLapsed
by Sumukh Infra · Borivali West, Mumbai 400103 · Map
- Launched
- Aug 20174 yrs 4 mths originally promised
- Possession (MahaRERA)
- Dec 2025Extended by 4 yrsWhat does Lapsed mean?
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 73 of 7992% · 69 rehab units
- Buildings
- 21 acre
- MahaRERA complaints
- 7Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale73 booked out of 79 units
Rehab69 units for existing members
Total 148 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 111
- 3 BHK
- 37
- Total units
- 148
- Buildings
- 2
- Land
- 1 acre
- Phases
- 1
- MahaRERA complaints
- 7
- Free-sale units
- 79
- Rehab units
- 69
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 95% | 73 | |
| 100% | 100% | 95% | 73 | |
| 100% | 100% | 95% | 71 | |
| 100% | 93% | 90% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Happy Home Chsl by Sumukh Infra is a 148-unit BMC-sanctioned project in Borivali West, Mumbai 400103, launched in August 2017; its MahaRERA registration has lapsed. 73 units booked out of 79 units for sale. The concrete structure (RCC) is complete.
Read full summary
Happy Home Chsl is a BMC-sanctioned project by Sumukh Infra in Borivali West, Mumbai 400103, registered with MahaRERA as P51800002652. It was launched in August 2017. It has 148 units in 2 buildings, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 148 units, 79 are for sale and 69 are rehab units for existing members.
Possession was due in December 2025, after an extension of 4 years from the original December 2021. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
73 units booked out of 79 units for sale (92%).