Nirmal Priti Chs Ltd, Mulund West

Ready to moveLapsed

by Tridevh Construction Company · Mulund West, Mumbai 400080 · Map

Launched
Aug 20174 yrs 4 mths originally promised
Possession (MahaRERA)
Dec 2025Extended by 4 yrsWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked (free sale)
5 of 5100%
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale5 booked out of 5 units

Land-owner share8 units, not for sale

Total 13 units. Land-owner units are not for sale.

Project facts

2 BHK
7
3 BHK
5
4 BHK
1
Total units
13
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
5
Land-owner share (not for sale)
8

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services97%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 95%Dec 2025: Final finishes 97%Jul 2026: Final finishes 97%Oct 2026: Final finishes 97%Excavation 100%Concrete structure (RCC) 100%Final finishes 97%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%97%5
100%100%97%5
100%100%97%5
100%100%95%5

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400080

Projects with up to 30 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400080
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 4 mths3 yrs 10 mths
Possession date extendedBy 4 yrs2 of 3
Possession date (MahaRERA)Dec 2025Aug 2024
Concrete structure (RCC)100%98%
Units booked (free sale)100%95%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Nirmal Priti Chs Ltd by Tridevh Construction Company is a 13-unit BMC-sanctioned project in Mulund West, Mumbai 400080, launched in August 2017; its MahaRERA registration has lapsed. 5 units booked out of 5 units for sale. The concrete structure (RCC) is complete.

Read full summary

Nirmal Priti Chs Ltd is a BMC-sanctioned project by Tridevh Construction Company in Mulund West, Mumbai 400080, registered with MahaRERA as P51800002769. It was launched in August 2017. It has 13 units in 1 building, with 2, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 13 units, 5 are for sale and 8 are the land-owner's share, not for sale.

Possession was due in December 2025, after an extension of 4 years from the original December 2021. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 97% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

5 units booked out of 5 units for sale (100%).