Shubh Mangal, Santacruz East

Lapsed

by Rajpurohit Builders LLP · Santacruz East, Mumbai 400098 · Map

Launched
Aug 20171 yr 10 mths originally promised
Possession (MahaRERA)
Jun 2023Extended by 4 yrsWhat does Lapsed mean?
Concrete structure
0%Early stage
Booked
19 of 3751%
Buildings
10.2 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
1
2 BHK
3
3 BHK
29
4 BHK
3
Other units
1
Total units
37
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%19
100%0%0%–
100%0%0%–
100%0%0%19

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Shubh Mangal by Rajpurohit Builders LLP is a 37-unit BMC-sanctioned project in Santacruz East, Mumbai 400098, launched in August 2017; its MahaRERA registration has lapsed. 19 units booked out of total 37 units. Work on the concrete structure (RCC) has not started.

Read full summary

Shubh Mangal is a BMC-sanctioned project by Rajpurohit Builders LLP in Santacruz East, Mumbai 400098, registered with MahaRERA as P51800002774. It was launched in August 2017. It has 37 units in 1 building: 36 homes (1 RK, 2 BHK, 3 BHK and 4 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in June 2023, after an extension of 4 years from the original June 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) not started, final finishes not started.

19 units booked out of total 37 units (51%).