Celestia, Andheri East
Lapsed
by Ariisto Developers Private Limited · Andheri East, Mumbai 400069 · Map
- Launched
- Aug 20178 yrs 4 mths promised
- Possession (MahaRERA)
- Dec 2025Not extendedWhat does Lapsed mean?
- Concrete structure
- 0%Early stage
- Booked
- 245 of 90027%
- Buildings
- 42.7 acres
- MahaRERA complaints
- 3Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 304
- 3 BHK
- 596
- Total units
- 900
- Buildings
- 4
- Land
- 2.7 acres
- Phases
- 1
- MahaRERA complaints
- 3
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 30% | 0% | 0% | 245 | |
| 30% | 0% | 0% | – | |
| 30% | 0% | 0% | – | |
| 30% | 0% | 0% | 245 |
"–" means MahaRERA shows no figure for that update.
About this project
Celestia by Ariisto Developers Private Limited is a 900-unit project in Andheri East, Mumbai 400069, launched in August 2017; its MahaRERA registration has lapsed. 245 units booked out of total 900 units. Work on the concrete structure (RCC) has not started.
Read full summary
Celestia is a project by Ariisto Developers Private Limited in Andheri East, Mumbai 400069, registered with MahaRERA as P51800002847. It was launched in August 2017. It has 900 units in 4 buildings, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2025. That date has passed and no extension has been recorded. Construction: excavation 30% complete, structure (RCC) not started, final finishes not started.
245 units booked out of total 900 units (27%).