Vaibhav Heights, Santacruz East

Ready to move

by Rsn Balaji Realtors P Ltd · Santacruz East, Mumbai 400055 · Map

Launched
Aug 20171 yr 4 mths originally promised
Possession (MahaRERA)
Apr 2020Extended by 1 yr 4 mths
Concrete structure
100%Ready to move
Booked
52 of 52100%
Buildings
20.3 acres
MahaRERA complaints
2Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
12
2 BHK
27
Other units
13
Total units
52
Buildings
2
Land
0.3 acres
Phases
1
MahaRERA complaints
2

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services95%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 93%Dec 2025: Final finishes 95%Jul 2026: Final finishes 95%Excavation 100%Concrete structure (RCC) 100%Final finishes 95%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%95%52
100%100%95%52
100%100%93%51

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400055

Projects with 10–80 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400055
MeasureThis projectSimilar projects
Launch to possession (as first promised)1 yr 4 mths4 yrs 6 mths
Possession date extendedBy 1 yr 4 mths4 of 6
Possession date (MahaRERA)Apr 2020Dec 2024
Concrete structure (RCC)100%64%
Units booked100%61%
MahaRERA complaints (filed by or against the builder)22

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Vaibhav Heights by Rsn Balaji Realtors P Ltd is a 52-unit BMC-sanctioned project in Santacruz East, Mumbai 400055, launched in August 2017 with possession due in April 2020. 52 units booked out of total 52 units. The concrete structure (RCC) is complete.

Read full summary

Vaibhav Heights is a BMC-sanctioned project by Rsn Balaji Realtors P Ltd in Santacruz East, Mumbai 400055, registered with MahaRERA as P51800002862. It was launched in August 2017. It has 52 units in 2 buildings: 39 homes (1 and 2 BHK) and 13 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Possession was due in April 2020, after an extension of 1 year 4 months from the original December 2018. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

52 units booked out of total 52 units (100%).