Rudra Paradise, Santacruz East
Lapsed
by R-Stone Design and Build Private Limited · Santacruz East, Mumbai 400055 · Map
- Launched
- Aug 20173 yrs 5 mths originally promised
- Possession (MahaRERA)
- Jul 2026Extended by 5 yrs 6 mthsWhat does Lapsed mean?
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 28 of 4661% · 20 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale28 booked out of 46 units
Rehab20 units for existing members
Total 66 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 30
- 3 BHK
- 28
- Other units
- 8
- Total units
- 66
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 46
- Rehab units
- 20
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 43% | 28 | |
| 100% | 100% | 43% | 28 | |
| 100% | 100% | 38% | 28 | |
| 100% | 52% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400055
Projects with 20–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 5 mths | 5 yrs 8 mths |
| Possession date extended | By 5 yrs 6 mths | 5 of 6 |
| Possession date (MahaRERA) | Jul 2026 | Mar 2025 |
| Concrete structure (RCC) | 100% | 92% |
| Units booked (free sale) | 61% | 83% |
| MahaRERA complaints (filed by or against the builder) | 0 | 1 |
The 6 projects
- Ekta Sra Chs, Santacruz East
- Silver heights, Santacruz East
- Moniz Shraddha Heights, Santacruz East
- Vaibhav Heights, Santacruz East
- Bluemoon Annexe, Santacruz East
- Sagar Avenue II G, Santacruz East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Ekta Sra Chs | August 2017 | July 2024 | 100% | 23 units booked out of 27 units for sale |
| Silver heights | August 2017 | April 2028 | 88% | 43 units booked out of total 55 units |
| Moniz Shraddha Heights | August 2017 | December 2025 | 91% | 20 units booked out of total 48 units |
| Vaibhav Heights | August 2017 | April 2020 | 100% | 52 units booked out of total 52 units |
| Bluemoon Annexe | August 2017 | December 2025 | 92% | 59 units booked out of 71 units for sale |
| Sagar Avenue II G | September 2017 | June 2023 | 57% | – |
About this project
Rudra Paradise by R-Stone Design and Build Private Limited is a 66-unit MHADA-sanctioned project in Santacruz East, Mumbai 400055, launched in August 2017; its MahaRERA registration has lapsed. 28 units booked out of 46 units for sale. The concrete structure (RCC) is complete.
Read full summary
Rudra Paradise is a MHADA-sanctioned project by R-Stone Design and Build Private Limited in Santacruz East, Mumbai 400055, registered with MahaRERA as P51800008159. It was launched in August 2017. It has 66 units in 1 building: 58 homes (2 and 3 BHK) and 8 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 66 units, 46 are for sale and 20 are rehab units for existing members.
Possession was due in July 2026, after an extension of 5 years 6 months from the original January 2021. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 43% complete.
28 units booked out of 46 units for sale (61%).