Maplle Plazza, Jogeshwari East
Lapsed
by Maplle Infraprojects Limited · Jogeshwari East, Mumbai 400060 · Map
- Launched
- Aug 20174 yrs 7 mths originally promised
- Possession (MahaRERA)
- Dec 2025Extended by 3 yrs 9 mthsWhat does Lapsed mean?
- Concrete structure
- 50%Mid-construction
- Booked
- 49 of 49100%
- Buildings
- 20.4 acres
- MahaRERA complaints
- 2Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 18
- 2 BHK
- 1
- Other units
- 30
- Total units
- 49
- Buildings
- 2
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 2
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 50% | 50% | 33% | 49 | |
| 50% | 50% | 33% | – | |
| 50% | 50% | 33% | – | |
| 50% | 50% | 33% | 49 |
"–" means MahaRERA shows no figure for that update.
About this project
Maplle Plazza by Maplle Infraprojects Limited is a 49-unit project in Jogeshwari East, Mumbai 400060, launched in August 2017; its MahaRERA registration has lapsed. 49 units booked out of total 49 units. The concrete structure (RCC) is 50% complete.
Read full summary
Maplle Plazza is a project by Maplle Infraprojects Limited in Jogeshwari East, Mumbai 400060, registered with MahaRERA as P51800002879. It was launched in August 2017. It has 49 units in 2 buildings: 19 homes (1 and 2 BHK) and 30 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2025, after an extension of 3 years 9 months from the original March 2022. That date has passed and no further extension has been recorded. Construction: excavation 50% complete, structure (RCC) 50% complete, final finishes 33% complete.
49 units booked out of total 49 units (100%).