Integrated Ahana, Ghatkopar West
Lapsed
by Integrated Spaces Limited · Ghatkopar West, Mumbai 400086 · Map
- Launched
- Aug 20171 yr 4 mths originally promised
- Possession (MahaRERA)
- Apr 2025Extended by 6 yrs 4 mthsWhat does Lapsed mean?
- Concrete structure
- 82%Mid-construction
- Booked (free sale)
- 9 of 1656% · 11 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale9 booked out of 16 units
Rehab11 units for existing members
Total 27 units. Rehab units are not for sale.
Project facts
- 1 RK
- 2
- 1 BHK
- 2
- 2 BHK
- 9
- 3 BHK
- 3
- 4 BHK
- 9
- Other units
- 2
- Total units
- 27
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 16
- Rehab units
- 11
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 82% | 60% | 9 | |
| 100% | 82% | 60% | 9 | |
| 100% | 82% | 60% | 9 | |
| 100% | 82% | 60% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Integrated Ahana by Integrated Spaces Limited is a 27-unit BMC-sanctioned project in Ghatkopar West, Mumbai 400086, launched in August 2017; its MahaRERA registration has lapsed. 9 units booked out of 16 units for sale. The concrete structure (RCC) is 82% complete.
Read full summary
Integrated Ahana is a BMC-sanctioned project by Integrated Spaces Limited in Ghatkopar West, Mumbai 400086, registered with MahaRERA as P51800002899. It was launched in August 2017. It has 27 units in 1 building: 25 homes (1 RK, 1 BHK, 2 BHK, 3 BHK and 4 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 27 units, 16 are for sale and 11 are rehab units for existing members.
Possession was due in April 2025, after an extension of 6 years 4 months from the original December 2018. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 82% complete, final finishes 60% complete.
9 units booked out of 16 units for sale (56%).