Hubtown Premiere Residences, Andheri East
by Hubtown Limited · Andheri East, Mumbai 400047 · Map
- Launched
- Aug 2017First of 2 phases
- Possession (MahaRERA)
- Jul 2029Not extended
- Concrete structure
- 7%Weighted across 2 phases
- Booked
- –
- Buildings
- 30.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 34
- 3 BHK
- 27
- 4 BHK
- 19
- Total units
- 80
- Buildings
- 3
- Land
- 0.1 acres
- Phases
- 2
- MahaRERA complaints
- 0
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Hubtown Premiere Residences - Tower 3 Early stage | P51800002977 | 26 | 0% | 0% | |
| Hubtown Premiere Residences - Tower 2 Mid-construction | P51800006839 | 54 | 10% | – |
Show updates by phase
Hubtown Premiere Residences - Tower 3 (P51800002977)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 0% | 0% | 0% | 0 | |
| 0% | 0% | 0% | 0 | |
| 0% | 0% | 0% | 0 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Hubtown Premiere Residences - Tower 2 (P51800006839)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 50% | 10% | 0% | – | |
| 50% | 10% | 0% | – | |
| 50% | 10% | 0% | – | |
| 50% | 10% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
About this project
Hubtown Premiere Residences by Hubtown Limited is an 80-unit BMC-sanctioned project in Andheri East, Mumbai 400047, registered with MahaRERA in 2 phases, with possession due in July 2029. The concrete structure (RCC) is 7% complete.
Read full summary
Hubtown Premiere Residences is a BMC-sanctioned project by Hubtown Limited in Andheri East, Mumbai 400047, registered with MahaRERA as 2 phases (P51800002977, P51800006839). The first phase was launched in August 2017. Together the phases have 80 units in 3 buildings, with 2, 3 and 4 BHK homes as registered with MahaRERA. Both phases are active on MahaRERA.
The registered possession date is July 2029; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 7% complete and final finishes 0% complete. Neither phase has its structure complete.
Hubtown's track record in Mumbai
MahaRERA projects registered 2017–2023 in Mumbai
| Projects registered with MahaRERA | 27 |
|---|---|
| Total units across these projects | 1,419 |
| Completed without extending the possession date | 11 |
| Completed after an extension | 0 |
| Lapsed | 10 |
| Under construction | 6 |
| Possession date extended on the builder's application | 2 |
| Typical time from launch to 100% structure | 7 years 4 months |
| MahaRERA complaints (filed by or against the builder), all Hubtown projects | 234 (14 of 27 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.