East Point, Ghatkopar East

Lapsed

by Vital Developers Pvt Ltd · Ghatkopar East, Mumbai 400075 · Map

Launched
Aug 20172 yrs 5 mths originally promised
Possession (MahaRERA)
Jan 2021Extended by 1 yrWhat does Lapsed mean?
Concrete structure
60%Mid-construction
Booked
–
Buildings
10.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
76
Total units
76
Buildings
1
Land
0.5 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation95%
Concrete structure (slabs)60%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 95%Dec 2025: Excavation 95%Jul 2026: Excavation 95%Dec 2024: Concrete structure (RCC) 60%Dec 2025: Concrete structure (RCC) 60%Jul 2026: Concrete structure (RCC) 60%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 95%Concrete structure (RCC) 60%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
95%60%0%–
95%60%0%–
95%60%0%69

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

East Point by Vital Developers Pvt Ltd is a 76-unit project in Ghatkopar East, Mumbai 400075, launched in August 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is 60% complete.

Read full summary

East Point is a project by Vital Developers Pvt Ltd in Ghatkopar East, Mumbai 400075, registered with MahaRERA as P51800002979. It was launched in August 2017. It has 76 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in January 2021, after an extension of 1 year from the original January 2020. That date has passed and no further extension has been recorded. Construction: excavation 95% complete, structure (RCC) 60% complete, final finishes not started.