Mircale Heritage, Jogeshwari West

by Citimake Builders Private Limtied · Jogeshwari West, Mumbai 400102 · Map

Launched
Aug 20178 yrs 10 mths originally promised
Possession (MahaRERA)
Jun 2031Extended by 5 yrs
Concrete structure
0%Early stage
Booked
49 of 17828% · 52 in Dec 2024
Buildings
11.8 acres
MahaRERA complaints
3Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
80
2 BHK
74
Other units
24
Total units
178
Buildings
1
Land
1.8 acres
Phases
1
MahaRERA complaints
3

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation50%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Oct 2026Dec 2024: Excavation 50%Oct 2026: Excavation 50%Dec 2024: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Oct 2026: Final finishes 0%Excavation 50%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
50%0%0%49
50%0%0%52

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400102

Projects with 70–350 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400102
MeasureThis projectSimilar projects
Launch to possession (as first promised)8 yrs 10 mths5 yrs 1 mth
Possession date extendedBy 5 yrs6 of 6
Possession date (MahaRERA)Jun 2031Sep 2025
Concrete structure (RCC)0%74%
Units booked28%77%
MahaRERA complaints (filed by or against the builder)320

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Mircale Heritage by Citimake Builders Private Limtied is a 178-unit SRA-sanctioned project in Jogeshwari West, Mumbai 400102, launched in August 2017 with possession due in June 2031. 49 units booked out of total 178 units. Work on the concrete structure (RCC) has not started.

Read full summary

Mircale Heritage is an SRA-sanctioned project by Citimake Builders Private Limtied in Jogeshwari West, Mumbai 400102, registered with MahaRERA as P51800002996. It was launched in August 2017. It has 178 units in 1 building: 154 homes (1 and 2 BHK) and 24 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is June 2031, extended by 5 years from the original June 2026. Construction: excavation 50% complete, structure (RCC) not started, final finishes not started.

49 units booked out of total 178 units (28%). Since the December 2024 update, the possession date has moved from June 2026 to June 2031.