Shikhar, Jogeshwari West

by Orbit Ventures Developers · Jogeshwari West, Mumbai 400102 · Map

Launched
Aug 2017First of 2 phases
Possession (MahaRERA)
Dec 2020 – Jun 2027Extended in both phases
Concrete structure
37%Weighted across 2 phases
Booked
–
Buildings
20.6 acres
MahaRERA complaints
38Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

3 BHK
139
4 BHK
10
5+ BHK
62
Total units
211
Buildings
2
Land
0.6 acres
Phases
2
MahaRERA complaints
38

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Shikhar A
Ready to move Lapsed
P5180000566672100%–
Shikhar B
Mid-construction
P518000082131395%4%
Show updates by phase

Shikhar A (P51800005666)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%–
100%100%100%–
100%100%100%53

"–" means MahaRERA shows no figure for that update.

Shikhar B (P51800008213)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%5%0%6
90%0%0%–
90%0%0%–
90%0%0%6

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)37%
Finishes, lifts and services34%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 93%Dec 2025: Excavation 93%Jul 2026: Excavation 93%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 34%Dec 2025: Concrete structure (RCC) 34%Jul 2026: Concrete structure (RCC) 34%Oct 2026: Concrete structure (RCC) 37%Dec 2024: Final finishes 34%Dec 2025: Final finishes 34%Jul 2026: Final finishes 34%Oct 2026: Final finishes 34%Excavation 100%Concrete structure (RCC) 37%Final finishes 34%

How to read construction stages

Compared with 6 similar projects in PIN 400102

Projects with 100–450 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400102
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 10 mths5 yrs 7 mths
Possession date extendedYes5 of 6
Possession date (MahaRERA)Dec 2020 – Jun 2027Dec 2027
Concrete structure (RCC)37%92%
Units booked–77%
MahaRERA complaints (filed by or against the builder)383

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Shikhar by Orbit Ventures Developers is a 211-unit BMC-sanctioned project in Jogeshwari West, Mumbai 400102, registered with MahaRERA in 2 phases, with possession dates from December 2020 to June 2027. The concrete structure (RCC) is 37% complete.

Read full summary

Shikhar is a BMC-sanctioned project by Orbit Ventures Developers in Jogeshwari West, Mumbai 400102, registered with MahaRERA as 2 phases (P51800005666, P51800008213). The first phase was launched in August 2017. Together the phases have 211 units in 2 buildings, with 3, 4 and 5+ BHK homes as registered with MahaRERA. On MahaRERA, 1 is lapsed and 1 is active.

The phases' registered possession dates run from December 2020 to June 2027; both phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 37% complete and final finishes 34% complete. Neither phase has its structure complete.