Shikhar, Jogeshwari West
by Orbit Ventures Developers · Jogeshwari West, Mumbai 400102 · Map
- Launched
- Aug 2017First of 2 phases
- Possession (MahaRERA)
- Dec 2020 – Jun 2027Extended in both phases
- Concrete structure
- 37%Weighted across 2 phases
- Booked
- –
- Buildings
- 20.6 acres
- MahaRERA complaints
- 38Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 3 BHK
- 139
- 4 BHK
- 10
- 5+ BHK
- 62
- Total units
- 211
- Buildings
- 2
- Land
- 0.6 acres
- Phases
- 2
- MahaRERA complaints
- 38
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Shikhar A Ready to move Lapsed | P51800005666 | 72 | 100% | – | |
| Shikhar B Mid-construction | P51800008213 | 139 | 5% | 4% |
Show updates by phase
Shikhar A (P51800005666)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | – | |
| 100% | 100% | 100% | – | |
| 100% | 100% | 100% | 53 |
"–" means MahaRERA shows no figure for that update.
Shikhar B (P51800008213)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 5% | 0% | 6 | |
| 90% | 0% | 0% | – | |
| 90% | 0% | 0% | – | |
| 90% | 0% | 0% | 6 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Compared with 6 similar projects in PIN 400102
Projects with 100–450 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 10 mths | 5 yrs 7 mths |
| Possession date extended | Yes | 5 of 6 |
| Possession date (MahaRERA) | Dec 2020 – Jun 2027 | Dec 2027 |
| Concrete structure (RCC) | 37% | 92% |
| Units booked | – | 77% |
| MahaRERA complaints (filed by or against the builder) | 38 | 3 |
The 6 projects
- A R B Heights, Jogeshwari West
- Lamor, Jogeshwari West
- Mircale Heritage, Jogeshwari West
- Verona, Jogeshwari West
- The Residency, Jogeshwari West
- Pearl Platinum, Jogeshwari West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| A R B Heights | August 2017 | December 2027 | 37% | 65 units booked out of total 203 units |
| Lamor | August 2017 | June 2023 | 97% | 232 units booked out of total 240 units |
| Mircale Heritage | August 2017 | June 2031 | 0% | 49 units booked out of total 178 units |
| Verona | August 2017 | December 2027 | 100% | 222 units booked out of total 290 units |
| The Residency | August 2017 | June 2023 | 100% | 115 units booked out of 128 units for sale |
| Pearl Platinum | August 2017 | Dec 2028 | 87% | – |
About this project
Shikhar by Orbit Ventures Developers is a 211-unit BMC-sanctioned project in Jogeshwari West, Mumbai 400102, registered with MahaRERA in 2 phases, with possession dates from December 2020 to June 2027. The concrete structure (RCC) is 37% complete.
Read full summary
Shikhar is a BMC-sanctioned project by Orbit Ventures Developers in Jogeshwari West, Mumbai 400102, registered with MahaRERA as 2 phases (P51800005666, P51800008213). The first phase was launched in August 2017. Together the phases have 211 units in 2 buildings, with 3, 4 and 5+ BHK homes as registered with MahaRERA. On MahaRERA, 1 is lapsed and 1 is active.
The phases' registered possession dates run from December 2020 to June 2027; both phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 37% complete and final finishes 34% complete. Neither phase has its structure complete.