DN Nagar Panchavati Co-operative Housing Society Limited- Gokul Panchavati, Andheri West
Lapsed
by Surya-Landmark Developers Private Limited · Andheri West, Mumbai 400053 · Map
- Launched
- Aug 20172 yrs 4 mths originally promised
- Possession (MahaRERA)
- Dec 2021Extended by 2 yrsWhat does Lapsed mean?
- Concrete structure
- 95%Mid-construction
- Booked
- 18 of 2090%
- Buildings
- 10.2 acres
- MahaRERA complaints
- 2Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 14
- 3 BHK
- 6
- Total units
- 20
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 2
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 95% | 30% | 18 | |
| 100% | 95% | 30% | – | |
| 100% | 95% | 30% | – | |
| 100% | 95% | 30% | 18 |
"–" means MahaRERA shows no figure for that update.
About this project
DN Nagar Panchavati Co-operative Housing Society Limited- Gokul Panchavati by Surya-Landmark Developers Private Limited is a 20-unit project in Andheri West, Mumbai 400053, launched in August 2017; its MahaRERA registration has lapsed. 18 units booked out of total 20 units. The concrete structure (RCC) is 95% complete.
Read full summary
DN Nagar Panchavati Co-operative Housing Society Limited- Gokul Panchavati is a project by Surya-Landmark Developers Private Limited in Andheri West, Mumbai 400053, registered with MahaRERA as P51800003226. It was launched in August 2017. It has 20 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2021, after an extension of 2 years from the original December 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 95% complete, final finishes 30% complete.
18 units booked out of total 20 units (90%).