Vinayak Shraddha Tower, Bandra East
Lapsed
by K K Krishnan Construction Company Pvt Ltd · Bandra East, Mumbai 400051 · Map
- Launched
- Aug 20175 yrs 7 mths originally promised
- Possession (MahaRERA)
- Dec 2025Extended by 2 yrs 9 mthsWhat does Lapsed mean?
- Concrete structure
- 80%Mid-construction
- Booked
- 19 of 3456%
- Buildings
- 30.5 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 RK
- 2
- 1 BHK
- 11
- 2 BHK
- 21
- Total units
- 34
- Buildings
- 3
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 80% | 62% | 19 | |
| 100% | 80% | 62% | – | |
| 100% | 80% | 62% | – | |
| 100% | 73% | 55% | 19 |
"–" means MahaRERA shows no figure for that update.
About this project
Vinayak Shraddha Tower by K K Krishnan Construction Company Pvt Ltd is a 34-unit project in Bandra East, Mumbai 400051, launched in August 2017; its MahaRERA registration has lapsed. 19 units booked out of total 34 units. The concrete structure (RCC) is 80% complete.
Read full summary
Vinayak Shraddha Tower is a project by K K Krishnan Construction Company Pvt Ltd in Bandra East, Mumbai 400051, registered with MahaRERA as P51800003341. It was launched in August 2017. It has 34 units in 3 buildings, with 1 RK, 1 BHK and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2025, after an extension of 2 years 9 months from the original March 2023. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 80% complete, final finishes 62% complete.
19 units booked out of total 34 units (56%).