Balaji Accolade, Mulund West

Lapsed

by Balaji Developers · Mulund West, Mumbai 400080 · Map

Launched
Aug 20171 yr 11 mths originally promised
Possession (MahaRERA)
Jul 2020Extended by 1 yrWhat does Lapsed mean?
Concrete structure
80%Mid-construction
Booked
–
Buildings
10.2 acres
MahaRERA complaints
3Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
33
Total units
33
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
3

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)80%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 80%Dec 2025: Concrete structure (RCC) 80%Jul 2026: Concrete structure (RCC) 80%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 80%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%80%0%–
100%80%0%–
100%80%0%33

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Balaji Accolade by Balaji Developers is a 33-unit project in Mulund West, Mumbai 400080, launched in August 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is 80% complete.

Read full summary

Balaji Accolade is a project by Balaji Developers in Mulund West, Mumbai 400080, registered with MahaRERA as P51800003420. It was launched in August 2017. It has 33 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in July 2020, after an extension of 1 year from the original July 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 80% complete, final finishes not started.