Skip to main content

Hubtown Premiere Residences - Commercial, Andheri East

Ready to move

by Hubtown Limited · Andheri East, Mumbai 400047 · Map

Launched
Aug 20178 yrs 11 mths promised
Possession (MahaRERA)
Jul 2026Not extended
Concrete structure
100%Ready to move
Booked
49 of 5983%
Buildings
10.3 acres
MahaRERA complaints
2Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
59
Total units
59
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
2

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 100%Dec 2025: Final finishes 100%Jul 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%49
100%100%100%–
100%100%100%34

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Hubtown Premiere Residences - Commercial by Hubtown Limited is a 59-unit BMC-sanctioned project in Andheri East, Mumbai 400047, launched in August 2017 with possession due in July 2026. 49 units booked out of total 59 units. The concrete structure (RCC) is complete.

Read full summary

Hubtown Premiere Residences - Commercial is a BMC-sanctioned project by Hubtown Limited in Andheri East, Mumbai 400047, registered with MahaRERA as P51800003575. It was launched in August 2017. It has 59 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active.

Possession was due in July 2026. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

49 units booked out of total 59 units (83%).

Hubtown's track record in Mumbai

MahaRERA projects registered 2017–2023 in Mumbai

Projects registered with MahaRERA27
Total units across these projects1,419
Completed without extending the possession date11
Completed after an extension0
Lapsed10
Under construction6
Possession date extended on the builder's application2
Typical time from launch to 100% structure7 years 4 months
MahaRERA complaints (filed by or against the builder), all Hubtown projects234 (14 of 27 projects)

See all Hubtown projects →