Crystal Heights, Jogeshwari West

Ready to moveLapsed

by Crystal Constructions · Jogeshwari West, Mumbai 400102 · Map

Launched
Aug 20174 yrs 11 mths originally promised
Possession (MahaRERA)
Dec 2025Extended by 3 yrs 5 mthsWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked
22 of 3367%
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
2
1 BHK
4
2 BHK
24
Other units
3
Total units
33
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services90%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 90%Dec 2025: Final finishes 90%Jul 2026: Final finishes 90%Oct 2026: Final finishes 90%Excavation 100%Concrete structure (RCC) 100%Final finishes 90%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%90%22
100%100%90%22
100%100%90%22
100%100%90%21

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Crystal Heights by Crystal Constructions is a 33-unit BMC-sanctioned project in Jogeshwari West, Mumbai 400102, launched in August 2017; its MahaRERA registration has lapsed. 22 units booked out of total 33 units. The concrete structure (RCC) is complete.

Read full summary

Crystal Heights is a BMC-sanctioned project by Crystal Constructions in Jogeshwari West, Mumbai 400102, registered with MahaRERA as P51800003672. It was launched in August 2017. It has 33 units in 1 building: 30 homes (1 RK, 1 BHK and 2 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2025, after an extension of 3 years 5 months from the original July 2022. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

22 units booked out of total 33 units (67%).