The Palms, Ghatkopar East

Lapsed

by Tanishq Builders · Ghatkopar East, Mumbai 400077 · Map

Launched
Aug 20173 yrs 10 mths originally promised
Possession (MahaRERA)
Dec 2025Extended by 4 yrs 6 mthsWhat does Lapsed mean?
Concrete structure
44%Mid-construction
Booked
92 of 19348%
Buildings
51.9 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
11
2 BHK
123
3 BHK
47
4 BHK
12
Total units
193
Buildings
5
Land
1.9 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)44%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 39%Dec 2025: Concrete structure (RCC) 44%Jul 2026: Concrete structure (RCC) 44%Oct 2026: Concrete structure (RCC) 44%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 44%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%44%0%92
100%44%0%–
100%44%0%–
100%39%0%92

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

The Palms by Tanishq Builders is a 193-unit MHADA-sanctioned project in Ghatkopar East, Mumbai 400077, launched in August 2017; its MahaRERA registration has lapsed. 92 units booked out of total 193 units. The concrete structure (RCC) is 44% complete.

Read full summary

The Palms is a MHADA-sanctioned project by Tanishq Builders in Ghatkopar East, Mumbai 400077, registered with MahaRERA as P51800003688. It was launched in August 2017. It has 193 units in 5 buildings, with 1, 2, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2025, after an extension of 4 years 6 months from the original June 2021. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 44% complete, final finishes not started.

92 units booked out of total 193 units (48%).