Kamala Chs Ltd, Kandivali West
Ready to moveLapsed
by Pravesh Kirti Kanther · Kandivali West, Mumbai 400067 · Map
- Launched
- Aug 20177 yrs 4 mths originally promised
- Possession (MahaRERA)
- Dec 2031Extended by 7 yrsWhat does Lapsed mean?
- Concrete structure
- 100%Ready to move
- Booked
- 107 of 11097%
- Buildings
- 10.2 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 39
- 2 BHK
- 63
- Other units
- 8
- Total units
- 110
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 1
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 90% | 107 | |
| 100% | 100% | 90% | – | |
| 100% | 100% | 90% | – | |
| 100% | 100% | 90% | 107 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400067
Projects with 50–250 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 7 yrs 4 mths | 3 yrs 8 mths |
| Possession date extended | By 7 yrs | 3 of 6 |
| Possession date (MahaRERA) | Dec 2031 | Jan 2023 |
| Concrete structure (RCC) | 100% | 55% |
| Units booked | 97% | 62% |
| MahaRERA complaints (filed by or against the builder) | 1 | 3 |
The 6 projects
- Gabadia Heights, Kandivali West
- Building on Sub Plot F of CTS No 283 A and 238 B of Kandivali West, Kandivali West
- Buildings on portion of Sub plot A CTS no 671A 662A 610A etc of Kandivali, Kandivali West
- Krishna, Kandivali West
- Building on portion of Sub plot D CTS no 625 A 4 625 B pt 627 A of Kandivali West Mumbai 67, Kandivali West
- Kalpavruksh Garden III, Kandivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Gabadia Heights | August 2017 | February 2022 | 60% | – |
| Building on Sub Plot F of CTS No 283 A and 238 B of Kandivali West | August 2017 | July 2027 | 43% | 84 units booked out of total 89 units |
| Buildings on portion of Sub plot A CTS no 671A 662A 610A etc of Kandivali | August 2017 | October 2020 | 100% | 81 units booked out of total 85 units |
| Krishna | August 2017 | December 2028 | 67% | 37 units booked out of total 121 units |
| Building on portion of Sub plot D CTS no 625 A 4 625 B pt 627 A of Kandivali West Mumbai 67 | August 2017 | December 2023 | 0% | 23 units booked out of total 146 units |
| Kalpavruksh Garden III | August 2017 | June 2021 | 50% | – |
About this project
Kamala Chs Ltd by Pravesh Kirti Kanther is a 110-unit project in Kandivali West, Mumbai 400067, launched in August 2017; its MahaRERA registration has lapsed. 107 units booked out of total 110 units. The concrete structure (RCC) is complete.
Read full summary
Kamala Chs Ltd is a project by Pravesh Kirti Kanther in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800003738. It was launched in August 2017. It has 110 units in 1 building: 102 homes (1 and 2 BHK) and 8 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Its registered possession date is December 2031, extended by 7 years from the original December 2024. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
107 units booked out of total 110 units (97%).