Morya Business Centre, Andheri East

Lapsed

by Morya Ace · Andheri East, Mumbai 400047 · Map

Launched
Aug 20175 yrs 5 mths originally promised
Possession (MahaRERA)
Jul 2024Extended by 1 yr 6 mthsWhat does Lapsed mean?
Concrete structure
0%Early stage
Booked
–
Buildings
11.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
58
Total units
58
Buildings
1
Land
1.1 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation55%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 55%Dec 2025: Excavation 55%Jul 2026: Excavation 55%Oct 2026: Excavation 55%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 55%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
55%0%0%–
55%0%0%–
55%0%0%–
55%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Morya Business Centre by Morya Ace is a 58-unit BMC-sanctioned project in Andheri East, Mumbai 400047, launched in August 2017; its MahaRERA registration has lapsed. Work on the concrete structure (RCC) has not started.

Read full summary

Morya Business Centre is a BMC-sanctioned project by Morya Ace in Andheri East, Mumbai 400047, registered with MahaRERA as P51800003866. It was launched in August 2017. It has 58 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in July 2024, after an extension of 1 year 6 months from the original January 2023. That date has passed and no further extension has been recorded. Construction: excavation 55% complete, structure (RCC) not started, final finishes not started.