La Maison, Khar West

Lapsed

by Paramvir Real Estates LLP · Khar West, Mumbai 400052 · Map

Launched
Aug 20176 yrs 4 mths promised
Possession (MahaRERA)
Dec 2023Not extendedWhat does Lapsed mean?
Concrete structure
0%Early stage
Booked
22 of 15015%
Buildings
12.1 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
72
3 BHK
72
Other units
6
Total units
150
Buildings
1
Land
2.1 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation95%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 95%Dec 2025: Excavation 95%Jul 2026: Excavation 95%Oct 2026: Excavation 95%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 95%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
95%0%0%22
95%0%0%–
95%0%0%–
95%0%0%22

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

La Maison by Paramvir Real Estates LLP is a 150-unit project in Khar West, Mumbai 400052, launched in August 2017; its MahaRERA registration has lapsed. 22 units booked out of total 150 units. Work on the concrete structure (RCC) has not started.

Read full summary

La Maison is a project by Paramvir Real Estates LLP in Khar West, Mumbai 400052, registered with MahaRERA as P51800003898. It was launched in August 2017. It has 150 units in 1 building: 144 homes (2 and 3 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2023. That date has passed and no extension has been recorded. Construction: excavation 95% complete, structure (RCC) not started, final finishes not started.

22 units booked out of total 150 units (15%).