Orchid, Juhu

Lapsed

by SiroyaFM Constructions Pvt Ltd · Juhu, Mumbai 400049 · Map

Launched
Aug 20172 yrs 2 mths promised
Possession (MahaRERA)
Oct 2019Not extendedWhat does Lapsed mean?
Concrete structure
60%Mid-construction
Booked
3 of 933%
Buildings
10.1 acres
MahaRERA complaints
2Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
9
Total units
9
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
2

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation90%
Concrete structure (slabs)60%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 90%Dec 2025: Excavation 90%Jul 2026: Excavation 90%Oct 2026: Excavation 90%Dec 2024: Concrete structure (RCC) 60%Dec 2025: Concrete structure (RCC) 60%Jul 2026: Concrete structure (RCC) 60%Oct 2026: Concrete structure (RCC) 60%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 90%Concrete structure (RCC) 60%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
90%60%0%3
90%60%0%–
90%60%0%–
90%60%0%3

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Orchid by SiroyaFM Constructions Pvt Ltd is a 9-unit project in Juhu, Mumbai 400049, launched in August 2017; its MahaRERA registration has lapsed. 3 units booked out of total 9 units. The concrete structure (RCC) is 60% complete.

Read full summary

Orchid is a project by SiroyaFM Constructions Pvt Ltd in Juhu, Mumbai 400049, registered with MahaRERA as P51800004021. It was launched in August 2017. It has 9 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in October 2019. That date has passed and no extension has been recorded. Construction: excavation 90% complete, structure (RCC) 60% complete, final finishes not started.

3 units booked out of total 9 units (33%).