Vaibhav CHS Ltd, Goregaon West

Lapsed

by Swastik Realty Pvt Ltd · Goregaon West, Mumbai 400104 · Map

Launched
Aug 201710 mths originally promised
Possession (MahaRERA)
Jun 2020Extended by 2 yrsWhat does Lapsed mean?
Concrete structure
56%Mid-construction
Booked
–
Buildings
20.3 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
2
1 BHK
1
2 BHK
38
3 BHK
2
Other units
16
Total units
59
Buildings
2
Land
0.3 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)56%
Finishes, lifts and services90%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 56%Dec 2025: Concrete structure (RCC) 56%Jul 2026: Concrete structure (RCC) 56%Dec 2024: Final finishes 90%Dec 2025: Final finishes 90%Jul 2026: Final finishes 90%Excavation 100%Final finishes 90%Concrete structure (RCC) 56%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%56%90%–
100%56%90%–
100%56%90%59

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Vaibhav CHS Ltd by Swastik Realty Pvt Ltd is a 59-unit MHADA-sanctioned project in Goregaon West, Mumbai 400104, launched in August 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is 56% complete.

Read full summary

Vaibhav CHS Ltd is a MHADA-sanctioned project by Swastik Realty Pvt Ltd in Goregaon West, Mumbai 400104, registered with MahaRERA as P51800004113. It was launched in August 2017. It has 59 units in 2 buildings: 43 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 16 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in June 2020, after an extension of 2 years from the original June 2018. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 56% complete, final finishes 90% complete.